<?xml version="1.0" encoding="UTF-8"?>
<rss version="2.0"
	xmlns:content="http://purl.org/rss/1.0/modules/content/"
	xmlns:wfw="http://wellformedweb.org/CommentAPI/"
	xmlns:dc="http://purl.org/dc/elements/1.1/"
	xmlns:atom="http://www.w3.org/2005/Atom"
	xmlns:sy="http://purl.org/rss/1.0/modules/syndication/"
	xmlns:slash="http://purl.org/rss/1.0/modules/slash/"
	>

<channel>
	<title>Effexis &#38; Goals To Action Blog &#187; Task Chooser</title>
	<atom:link href="http://effexis2.com/blog/tag/task-chooser/feed/" rel="self" type="application/rss+xml" />
	<link>http://effexis2.com/blog</link>
	<description>Achieve Planner, Productivity And Goal Achievement Tips &#38; Strategies</description>
	<lastBuildDate>Mon, 24 Jan 2011 23:25:40 +0000</lastBuildDate>
	<language>en</language>
	<sy:updatePeriod>hourly</sy:updatePeriod>
	<sy:updateFrequency>1</sy:updateFrequency>
	<generator>http://wordpress.org/?v=3.3.2</generator>
		<item>
		<title>Using The Next Action List</title>
		<link>http://effexis2.com/blog/using-the-next-action-list/</link>
		<comments>http://effexis2.com/blog/using-the-next-action-list/#comments</comments>
		<pubDate>Tue, 10 Nov 2009 22:07:27 +0000</pubDate>
		<dc:creator>Rodger Constandse</dc:creator>
				<category><![CDATA[Advanced]]></category>
		<category><![CDATA[GTD]]></category>
		<category><![CDATA[Next Actions]]></category>
		<category><![CDATA[Outline]]></category>
		<category><![CDATA[Task Chooser]]></category>

		<guid isPermaLink="false">http://effexis2.com/blog/?p=36</guid>
		<description><![CDATA[Achieve Planner supports the concept of a ‘Next Action List’ for projects in the master Outline and Task Chooser. In this article, I&#8217;m going to show you how to create and plan a project for a birthday party, and then use the Next Action List to focus in on the next actions for this project. [...]]]></description>
			<content:encoded><![CDATA[<p>Achieve Planner supports the  						concept of a <strong>‘Next Action List’</strong> for projects in the  						master Outline and Task Chooser.</p>
<p>In this article, I&#8217;m going to show you  						how to create and plan a project for a birthday party,  						and then use the Next Action List to focus in on the  						next actions for this project.</p>
<p>Here is what the birthday party  						project looks like in the Outline:</p>
<p align="center"><img src="http://www.effexis.com/achieve/training/nextactions/party-planning-project.png" border="0" alt="" width="373" height="295" /></p>
<p>The main ‘Plan Party’ project has  						three sub-projects, ‘Make Reservations’, ‘Order Cake’,  						and ‘Print Invitations’.</p>
<p>The reason these are sub-projects is  						that they represent multi-step parts of the main project  						that are somewhat independent of each other, and one  						could conceivably make progress on them in parallel.</p>
<p>Depending on your preferences, and how  						you use Achieve Planner, you could also represent them  						as top-level tasks of the ‘Plan Party’ project instead  						of sub-projects.</p>
<h2><strong>Viewing the Next Action List in the  						Outline</strong></h2>
<p>You can toggle the display of the  						‘Next Action List’ in the master outline using the Next  						Actions Only checkbox available in the Outline tab, or  						using the equivalent keyboard shortcut (Ctrl+Shift+8).</p>
<p align="left">When the ‘Next Action  						Only’ mode is enabled, the outline is filtered so that  						only ‘next action’ tasks are displayed under each  						project.</p>
<p align="left">There are two definitions of  						‘Next Actions’ for this list: a simpler ‘basic’ version for new  						users, and an ‘advanced’ version for more experienced  						users who want more freedom in defining what a next  						action is.</p>
<p align="left">You can change the  						definition of ‘Next Action’ used by Achieve Planner in  						the Next Actions tab of the Options Dialog (Tools -&gt;  						Options) as I describe later in this article.</p>
<p align="left"><strong>Using the Basic ‘Next  						Action’ Definition</strong></p>
<p align="left">By default, ‘Next Action’  						tasks are defined as the highest priority tasks under each project  						in the Outline priority sort order.</p>
<p align="left">This is what the ‘Plan  						Party’ project would look like with the Next Actions  						List filter turned on.</p>
<p align="center"><img src="http://www.effexis.com/achieve/training/nextactions/basic-na-list.png" border="0" alt="" width="436" height="168" /></p>
<p>You’ll notice that the Outline now  						only shows one task under each sub-project following the  						Outline priority sorting order.</p>
<p>NOTE: Starting with the 1.9.6 release,  						if you have multiple A1 tasks under a project, they will  						ALL show up as Next Actions since they all share the  						highest priority. This definition allows you to have  						multiple next actions under a single project.</p>
<p>When you complete a task in any of  						these sub-projects, the next available task under that  						project is displayed. For example, this is what the  						outline looks like when you’ve completed the ‘Find  						location’ task of the Make Reservations project…</p>
<p align="center"><img src="http://www.effexis.com/achieve/training/nextactions/basic-na-list-task-complete.png" border="0" alt="" width="431" height="169" /></p>
<p>You can see the next action ‘Call to  						make reservations’ is now in the list.</p>
<p><strong>Next Action Settings</strong></p>
<p>The Options dialog (Tools -&gt; Options)  						has some settings that control the display of the Next  						Action List in the Outline and Task Chooser.</p>
<p align="center"><img src="http://www.effexis.com/achieve/training/nextactions/options-dialog.png" border="0" alt="" width="391" height="155" /></p>
<p><strong>‘Use task predecessor for “Next  						Action Only” lists’</strong> controls whether to use the  						<em>basic</em> (unchecked) or <em>advanced</em> (checked) definition of  						‘Next Action.’ It’s set to basic definition by default.</p>
<p><strong>‘Hide Result Areas that don’t  						contain children’</strong> controls whether to hide result  						areas that don’t contain children when displaying the  						Next Action list in the master outline.</p>
<p><strong>‘Hide D priority items in “Next  						Actions Only” list’</strong> controls the display of D  						priority items (and their descendants) in the Next  						Action list of the master outline. If the box is  						checked, then D priority items and their descendants  						will not be included in the next actions list.</p>
<p>If <strong>‘Filter Outline to only show  						items with tasks’</strong> is checked, whenever the ‘Next  						Actions Only’ mode is turned on, the Outline tab will  						automatically be filtered in the Icon column so that  						only items containing tasks are included in the list.</p>
<p>The filter is automatically removed  						when ‘Next Actions Only’ mode is turned off. You can use  						this setting to control the display of  						projects/sub-projects that don’t have any next actions  						available.</p>
<p><a href="http://www.effexis.com/achieve/download.htm">Click here to download</a> a free 30 day trial  						of Achieve Planner to test drive this feature and see if  						it will work for you.</p>
<p><strong>Using the Advanced ‘Next Action’  						Definition</strong></p>
<p>If you want more control over which  						tasks are ‘Next Actions,’ you can use the advanced  						definition by enabling it from the Options dialog.</p>
<p>With the advanced definition, ‘Next  						Action’ tasks are defined as tasks that either don’t  						have predecessor tasks defined or that only have  						completed predecessor tasks.</p>
<p>In the birthday party planning project  						example, let’s say that the predecessor relationships  						between the various tasks look like this…</p>
<p align="center"><img src="http://www.effexis.com/achieve/training/nextactions/PartyProject.gif" border="0" alt="" width="500" height="392" /></p>
<p>In this diagram, each box represents a  						task and the arrows point to the predecessor task. For  						example, before you can do the ‘Print Invitations’ task,  						you must do the ‘Make Invitation List’ task first.  						That’s why ‘Make Invitation List’ is the predecessor.</p>
<p>As you can see, you can have  						predecessor tasks in a different project. In this  						example, ‘Make Invitation List’ is also a predecessor  						for ‘Find Location’, because you can’t find a suitable  						location until you know how many people are invited.</p>
<p>You can establish the task predecessor  						relationship between tasks using the Task Predecessor  						field/column available in the Outline and Tasks tabs.</p>
<p>The Task Predecessor column is  						available in the ‘Active Planning’ view of the Outline.  						You can also add it to any of the other views using the  						‘View -&gt; Customize Current View’ command.</p>
<p>This is how you would represent these  						predecessor relationships in the Active Planning view of  						the Outline.</p>
<p align="center"><img src="http://www.effexis.com/achieve/training/nextactions/advanced-na-predecessors.png" border="0" alt="" width="549" height="317" /></p>
<p>You can see the relationships between  						the tasks in the Predecessor column. For example, you  						can see that ‘Make invitation list’ is a predecessor for  						‘Find location’, ‘Select from catalog’ and ‘Print  						invitations’ because its task row number (#16) is in the  						predecessor column for these three tasks.</p>
<p>There are two ways to establish a  						predecessor relationship between two tasks:</p>
<p>1) Enter the Row Number (the number in  						the gray header at the start of each row) of the  						predecessor task in the Task Predecessor cell for the  						dependent task.</p>
<p>For example, task # 16 ‘Make  						invitation list’ is a predecessor of Task # 17 ‘Print  						invitations’ because the number 16 is in the Task  						Predecessor cell for row # 17.</p>
<p>2) Another way to establish  						predecessor relationship between tasks is to use the  						Actions -&gt; Link Tasks command, which helps you establish  						this type of predecessor relationship based on the order  						of the tasks in the Outline.</p>
<p>You need to select all the task rows  						that you want to link, and then use the Actions -&gt; Link  						Tasks command to link them in the order they appear in  						the Outline.</p>
<p>Here is what the Next Actions List for  						the party planning project looks like when you turn the  						‘Next Actions Only’ mode on using the advanced next  						action definition that uses task predecessors.</p>
<p align="center"><img src="http://www.effexis.com/achieve/training/nextactions/advanced-na-filtered.png" border="0" alt="" width="530" height="125" /></p>
<p>You can see that ‘Make invitation  						list’ is the only task shown. The list also includes  						sub-projects ‘Make Reservations’ and ‘Order Cake’ since  						they are sub-projects rather than tasks.</p>
<p>Having these ‘empty’ sub-projects in the list reminds  						you that there are parts of the Plan Party project that  						you can’t advance because you don’t have any available  						next actions.</p>
<p>NOTE: You can choose not to see these ‘empty’  						sub-projects by changing some of the settings as I  						describe later in the tutorial.</p>
<p>Here’s what the list looks like when you complete the  						‘Make invitation list’ task.</p>
<p align="center"><img src="http://www.effexis.com/achieve/training/nextactions/advanced-na-task-complete.png" border="0" alt="" width="532" height="189" /></p>
<p>The previously dependent tasks are  						showing as next actions because their predecessor task  						is now completed.</p>
<p>The ‘OOV’ in the Predecessor field indicates an  						“out-of-view” predecessor that is not visible in the  						current view. In this case, this is the task you just  						completed that is not visible in the Active views. To  						change or remove these predecessors, switch to the &#8216;All  						Items&#8217; view.</p>
<p><strong>Filtering ‘Empty’ Projects &amp; Sub-Projects</strong></p>
<p>To automatically hide empty projects and sub-projects  						from the Next Actions Only display, you need to enable  						the ‘Filter Outline to only show items with tasks’  						setting in the Options dialog.</p>
<p>Here is what the original Next Action Only list  						(advanced NA definition) looks like when this setting is  						enabled.</p>
<p align="center"><img src="http://www.effexis.com/achieve/training/nextactions/advanced-na-only-with-tasks.png" border="0" alt="" width="531" height="104" /></p>
<p>As you can see, the ‘empty’  						sub-projects under the Plan Party project are now  						filtered out of the display. You can tell that the  						column filter is active because the funnel icon on the  						Icon column header is blue.</p>
<p>You can change or disable this filter manually by  						clicking on this funnel icon and selecting (All) from  						the dropdown.</p>
<p><strong>Multiple ‘Next Actions’ Under a  						Project</strong></p>
<p>One of the advantages of the  						‘advanced’ next action definition is that it allows you  						to have multiple Next Actions under a project or  						sub-project based on the task predecessors.</p>
<p>For example, if we add a ‘Buy Stamps’  						action to the ‘Print invitations’ sub-project that is  						independent of the ‘Print invitations’ action, the  						resulting Outline would look like this:</p>
<p align="center"><img src="http://www.effexis.com/achieve/training/nextactions/advanced-na-multiple-predecessors.png" border="0" alt="" width="533" height="316" /></p>
<p>Also notice that we’ve now made Task  						‘Send out invitations’ (#19) dependent on both ‘Print  						invitations’ (#17) and ‘Buy stamps’ (#18) because you  						can’t send out the invitations until you do both.</p>
<p>Here’s what the Next Action List looks  						like when you complete the ‘Make invitation list’ task:</p>
<p align="center"><img src="http://www.effexis.com/achieve/training/nextactions/advanced-na-multiple-filtered.png" border="0" alt="" width="534" height="189" /></p>
<p>You can see that both ‘Print  						invitations’ and ‘Buy stamps’ are now shown as possible  						next actions. Furthermore, ‘Send out invitations’ will  						only be displayed in the Next Action List when both of  						these tasks are completed.</p>
<p>NOTE: You can accomplish something  						similar in the basic next action list by having multiple  						tasks with the highest priority.</p>
<h2><strong><a name="NextActionListTaskChooser">Viewing Next Actions in Task Chooser</a></strong></h2>
<p>The  						Task Chooser can also be used to display a ‘Next Actions  						Only’ list by changing some of its task chooser settings  						for a view.</p>
<p>Checking the “Only show next action(s)  						for project” limits the display of tasks in the task  						chooser to next actions using the same interpretation  						used in the Outline with the following exceptions:</p>
<p>1) The task chooser next action  						setting can be overridden at the project level using a  						checkbox available in the Project Information form’s  						general page</p>
<p>2) To produce the same next action  						list as the Outline when using the ‘basic’ definition of  						next action, you also need to check the “Use task  						priority order for next project actions” box in the  						settings.</p>
<p><strong>Using the ‘Basic’ Next Action  						Definition</strong></p>
<p>For the basic next action definition,  						you just need to check both of the boxes in the Task  						Chooser settings for the current view…</p>
<p align="center"><img src="http://www.effexis.com/achieve/training/nextactions/tc-na-settings.png" border="0" alt="" width="447" height="214" /></p>
<p>Here is what the task chooser looks  						like with these settings changes for the “Best Personal”  						view of the task chooser…</p>
<p align="center"><img src="http://www.effexis.com/achieve/training/nextactions/tc-na-basic-filtered.png" border="0" alt="" width="514" height="160" /></p>
<p><strong>Using the Advanced Next Action  						Definition</strong></p>
<p>For the advanced Next Action  						definition, the same setting “Only show next action(s)  						for projects” needs to be checked in the task chooser  						views, but the “Use task priority order for next project  						actions” <strong>needs to be UNCHECKED</strong>.</p>
<p>Here is what the Next Action list  						looks like in the task chooser when the advanced  						definition is enabled in the Options.</p>
<p align="center"><img src="http://www.effexis.com/achieve/training/nextactions/tc-na-advanced-filtered.png" border="0" alt="" width="507" height="118" /></p>
<p>Now only the ‘Make invitation list’  						task is shown because the task predecessors are hiding  						the other two tasks shown in the previous view.</p>